Required role: Technicians can update the status of work orders assigned to them. Admins and Managers can update any work order.

Steps

1

Open the work order

In Maintenance → Work Orders, click the work order you want to update.
2

Change the status

Click the Status dropdown and select the new status:
StatusWhen to use
OpenCreated, not yet started
In ProgressWork has begun
On HoldPaused — waiting on parts, access, or approval
CompletedWork is finished
CancelledWork order is no longer needed
3

Add a note (optional)

Add a note explaining the status change — for example, “Waiting on replacement part” or “Completed. Replaced door handle.”
4

Save

Click Save. The status update and note will be logged in the work order’s activity history.

Completing a work order

When marking a work order as Completed, you’ll be prompted to enter a completion summary. See Complete a Work Order for a full walkthrough.

Next steps

Complete a Work Order

Record the outcome when a work order is finished.